New Northfield Board Commissions Stormwater Study

Trustees also approved construction contracts in their monthly meeting Tuesday.

Northfield's village council saw a changing of the guard Tuesday night before trustees got down to village business.

Trustees commissioned a stormwater study by Christopher Burke Engineering for $20,000. The new study will build on a previous study completed in 2009 that developed a plan for minor projects that could be done to improve the village's system for handling flood water.

"The next chance is to say, 'what is the best way to approach the installation of this infrastructure," said Stacy Sigman, village manager.

Find out what's happening in Winnetka-Glencoewith free, real-time updates from Patch.

The board approved the lease of a Vac Con Sewer Cleaner from E.J. Equipment of Elmhurst, Ill. The payable amount is not to exceed $324,000. The interest rate of the five-year lease is 1.9597 percent. As part of the resolution, the board also approved the selling of the old sewer cleaner.

The board also approved the purchase of a truck scale from Advanced Weighing Systems to replace the Village's current 30-year-old model. The new scale should cost around $15,000.

Find out what's happening in Winnetka-Glencoewith free, real-time updates from Patch.

Finally, the board awarded a bid to Instituform Technologies of Chesterfield, Mo., to undertake the Sanitary Sewer Lip Lining Project. The project should around $277,000.

Upcoming events:
    •    May 30: Village offices will be closed on Memorial Day
    •    June 13: Architectural Commission Meeting at 7 p.m.
    •    June 21: Committee of the Whole meeting at 5:30 p.m.
    •    June 21: The next meeting of the Village Board at 7 p.m.

We’ve removed the ability to reply as we work to make improvements. Learn more here

The views expressed in this post are the author's own. Want to post on Patch?